2010-05-20

Meetings are monthly every third Thursday of the month at 1:30 Eastern time.
Call: (712) 432-0175, access code 992610#

Attending: Susan, Jonathan, Cris, Tim, Parker

Absent: Tuy

Status of incubating projects

Key

Summary

Assignee

Project Lead

Status

Created

Updated

INC-15

Content Management Portlet

Christopher J. Holdorph

Misagh Moayyed

Last code changes made on Nov 30, 2009 - touch base with Jen and possibly revert to sandbox if no expected progress next

27/May/09

18/Nov/09

INC-8

Web Proxy Portlet

Christopher J. Holdorph

Eric Dalquist

No license or notice file yet.  code base is active and changing.

28/Jan/09

18/Nov/09

INC-7

Functional Tests Portlet

Christopher J. Holdorph

Eric Dalquist

Made some minor updates to the INC-7 jira ticket for this, but nothing substantial has changed.

28/Jan/09

18/Nov/09

INC-13

Bedework

Jonathan Markow

Gary Schwartz

sponsored but tasks remain to be completed by 3.7 release - active work is taking place

15/Apr/09

03/May/10

INC-11

esup-helpdesk

Jonathan Markow

Pascal Aubry

production pilot underway but still confidential; if successful, they will use it

02/Mar/09

03/May/10

INC-9

OpenRegistry

Jonathan Markow

Benn Oshrin

RU in transition.  Jonathan visited and spoke with them and they intend to continue.  Phone call to RU and Simon Fraser planned with Jonathan.

08/Feb/09

03/May/10

INC-6

Bookmarks Portlet

Parker Grimes

Eric Dalquist

No change.

28/Jan/09

18/Nov/09

INC-2

Weather Portlet

Parker Grimes

Parker Grimes

I still need commit access in subversion so I can get things done.

27/Jan/09

18/Nov/09

INC-20

Email Preview Portlet

Susan Bramhall

Jen Bourey

moving gradually from Unicon authorship to wider community. Appears about 50% complete.

20/Apr/10

21/Apr/10

INC-19

.NET CAS Client

Susan Bramhall

Marvin S. Addison

jira issues created for outstanding tasks.  Mostly these relate to licensing and question of whether .NET can be part of the name. .NET can be part of name.

17/Mar/10

10/May/10

INC-18

NewsReaderPortlet

Susan Bramhall

Anthony Colebourne

No changes, numerous tasks need to be completed

10/Mar/10

16/Apr/10

INC-4

Facebook Connect Portlet

tim carroll

Erik Olsson

not much contact with Eric over the last month or two.  He is back so can try again.

27/Jan/09

18/Nov/09

INC-3

Announcements Portlet

tim carroll

Erik Olsson

not much contact with Eric over the last month or two.  He is back so can try again.

27/Jan/09

12/Jan/10

INC-17

Widget Portlets

Tuyhang Ly

Jen Bourey

- LICENSE & NOTICE files not yet in place

21/Feb/10

20/May/10

INC-16

Search Portlet

Tuyhang Ly

Jen Bourey

- Jira issue tracker not yet being used
- Project roadmap is in confluence, but empty

17/Feb/10

20/May/10

INC-5

Calendar Portlet

Tuyhang Ly

Jen Bourey

No changes

27/Jan/09

20/May/10

Other topics

Conversation with Apache did not happen.  Susan still wondering if QA is part of incubation.  Should we put this on Apache incubation question list for discussion?  (star) Susan will draft questions and submit

Cris - file upload portlet from UI for incubation?  Tim is willing to put that into incubation.  It is very uPortal specific so maybe better as framework portlet. 

Tim also planning to submit confluence wiki portlet.

U of Chicago will be submitting IT Ecosystem application.  There are interested in making it into a web app (rather than desktop application) so looking for collaborators.  Some other schools are already interested.

Action Items

(star) Susan ask Eric for progress on portlets for which he is project lead. Outline tasks for each.

(star) Parker file ICLA

(star) Cris check subversion access process

(star) Susan will draft questions and submit to general@incubator.apache.org

(star) Tim suggest to dev list / uPortal steering committee that incorporation of upload portlet as uPortal framework makes more sense than independent portlet.

(star) All - contact project leads in time for progress before next call.