Target Dates | Task | Status |
---|---|---|
Feb 06 | Start with seed of core institutions and players | in progress completed |
March 06 | Seed library with lists | in progress completed |
Spring Dev Meeting | Follow up at uP developers meeting
| in progress completed |
May 06 | Put out for community review before JA-SIG conference
| completed |
Summer uPortal Conference | Solicit contributions and feedback at JA-SIG 2006 Summer Conference
|
|
July 06 | incorporate conference contributions and feedback
|
|
Fall Dev Meeting | use to build roadmap at Fall developers meeting | completed |
Winter JA-SIG Conference | Update requirements library and gather information on community priorities and needs/requests |
|
...